Construction Updates

THE RESIDENCES CONSTRUCTION UPDATE JANUARY 2019

Pointcorp Commercial in consultation with all the stakeholders have made significant progression in construction and design development.

During the month of December 2018, the Tower Crane was erected on site and the pouring of Pad Footings continued.
The Basement 2 Slab pour commenced with the remaining pour predicted to take place in early January and completed in early February.

Specific design elements continued to progress in December with Pointcorp Commercial engaging a façade lighting supplier. The design will likely be finalised in early February.

Lobby areas, Lower Ground and Mezzanine areas are in full design mode with multiple consultants with varying disciplines working to perfect these areas and ensure the outcomes are in line with all stakeholder’s expectations.

Construction will continue to progress in line with the current construction programme.