FABRIC CONSTRUCTION UPDATE JUNE 2018

Progress on site during June has been great to see the crane up and second ground slab being poured on basement level 2. Formwork has also commenced as per the last photo so the builder is now on their way back up out of the hole.
Structural columns and slabs will continue now along with masonry blockwork so progress will be a lot more noticeable each month especially with some fine weather. We are hopeful of being back up at ground level by the end of the month.