THE MAXWELL CONSTRUCTION UPDATE OCTOBER 2017

The structure at The Maxwell continues to progress well. Last Thursday, the concrete slab was poured for Level 1. This week despite a few rain interruptions has seen the installation of all precast elements for this level. The Level 2 formwork will commence construction within the next 2 days weather permitting.

The installation of precast panels onsite give the first glimpse of the external makeup of the building. Standing on level 1, the Brisbane River can be seen wrapping around New Farm with the CBD and Kangaroo Point in the background. We are looking forward to seeing the view from Level 2 and 3 in coming weeks.