Construction Updates

THE MAXWELL CONSTRUCTION UPDATE NOVEMBER 2017

We are excited to announce that tomorrow the roof deck slab will be completed. This effectively is the structure of the building complete and our first chance to stand on the deck and appreciate the magnificent view. Internally the ceilings and partitions contractor is progressing well framing and building the walls of each unit. Within the next few weeks we expect to see some of the finishing trades commence including tiling and kitchen cabinets.

Despite the recent run of bad weather we are still tracking in line with the original construction programme and are forecasting completion in May 2018.