MAGNUS CONSTRUCTION UPDATE JUNE 2017

May was a busy month at Magnus. Significant structural progress has been made with the completion of Levels 2 and 3 concrete slabs and Level 4 due for completion later this week.  The Magnus’ signature precast concrete façade is starting to appear above the skyline of Kangaroo Point. In addition to these significant structural milestones, several milestones have been reached internally. Ceiling and partition trades have commenced on ground floor and level 1. Plumbers, electricians and mechanical contractors are also involved in the rough in of services on these lower levels. Behind the scenes, design and procurement activities are continuing as planned with final finishes selections being made and final sourcing being undertaken.

Project completion is scheduled for February 2018.