Construction Updates

MAGNUS CONSTRUCTION UPDATE JULY 2017

June was a big month for the site with the completion of the Level 7 slab and commencement of the internal works on Ground, Level 1 and Level 2. We will continue to keep you updated on the progress of the structure but the real attention now turns to the completion of the internal works. Level 1 and level 2 have both been framed and services rough in commenced. Within the next two weeks, walls on these levels will be sheeted with plasterboard, set and sanded ready for painting and commencement of floor finishes and joinery.

We are currently progressing in line with Programme and are forecasting project completion for Q1 2018.